Calderys Deutschland successfully completed the installation of a 110 tonne round melting furnace and a 110 tonne holding furnace for Gautschi Engineering GmbH at the customer Xiashun in Xiamen, China. In addition, an exhaust gas channel, measuring approximately 12m, a 23m stack, and 4 mobile burners for the melting furnace were installed.

The melting furnace as well as the holding furnace was installed with a combination of refractory bricks and castables. The insulation consists of bricks, concrete, and fibre material. The burner blocks as well as complicated geometrical surfaces were installed with castable refractories. The removable roof is made from bricks. 

The upper ring, which carries the lid, was installed from precast pieces produced at the Neuwied plant, just as the the precast pieces for the round shapes at the door opening.

The exhaust channel was mounted on-site in several steps with cast concrete. The 4 moveable burners were installed on-site with precast pieces, produced in Neuwied, and cast concrete.

This line 2 was started up following the successful installation of Line 1 some years prior, proving the value of Calderys project services that keep customers coming back for more.
 

Aluminium Project China - Refractory Bricks

 

Latest news

Retrouvez Calderys USA au stand numéro 802 lors de la Conférence sur le ciment IEEE-IAS PCA 2018. À bientôt !

4月23-24日與凱得力團隊相約第10屆圣彼得堡國際PetroCem會議:展位 #7。

Meet our Calderys USA experts at the API Fall Refining & Equipment Standards Meeting in Atlanta, Georgia.

欢迎莅临凯得力美国展位,探讨炼油和石化产品耐火材料。

Calderys Deutschland freut sich auf Ihren Besuch, Stand Nr. 1, auf dem Internationalen Feuerfest-Kolloquium 2018, das am 26. und 27. September im EUROGRESS in Aachen, Deutschland, stattfindet.